SW Mapp Road Resurfacing & Drainage Improvements (Multi-Modal)

Project scopes consists of finalizing a SFWMD permitted design to implement drainage relief to Old Palm City via stormwater retention pond and ultimately Danforth Creek. The project includes the addition of bike lanes, remove/replace existing failing pipes, resurfacing and drainage conveyance.

Dept:
PWD
District:
District 5
Status:
Active/Under Construction
Project Type:
Road Construction
Project Number:
101716
Current Status:
Drainage work in progress; Roadwork in progress; Patching roadway pipe crossings
Invoice Routing:
Katie Fulks
Budget:
$2,200,000
Photo Gallery:
Project Contact:
Paul Bangs, Krysti Brotherton - Design; Logan Huber - Construction
Construction Start Date:
2017-07
Construct. % Complete:
85%
Construction End Date:
2018-04
Design Start Date:
2016-04
Design % Complete:
100%
Design End Date:
2017-01
Location:
Mapp Road from Martin Highway / CR-714 to Martin Downs / SR-714
Project Coordination:
ADM, USD
Project Team:
Crossroads Environmental, Terracon Consultants, Mancil's Tractor
Project Inspector:
Rene Fresneda