All American Blvd at SW St. Lucie Shores

This project involves replacement of the existing 15” diameter corrugated metal pipe with 15” diameter reinforced concrete pipe on SW All American Blvd at SW St Lucie Shores Drive. The project is expected to take 3 weeks to complete. This work requires intermittent lane closures, and motorists should anticipate potential delays.

Dept:
PWD
District:
District 5
Status:
Completed
Project Type:
Stormwater
Construction Start Date:
This project is expected to begin November 18, 2013 for 3 weeks ending around December 9th, 2013.