34th Street SW - Water Main Interconnect

Water main interconnect between existing mains to provide looping redundancy.

Dept:
USD
District:
District 5
Status:
Completed
Project Type:
Utilities
Current Status:
Price proposals from Martin County Utilities annual underground contractors were opened on July 31, 2014. The purchase order was issued on August 1, 2014. FDEP construction permit was issued on July 23, 2014. Construction shop drawings were reviewed and approved on September 4, 2014. A Notice To Proceed with construction was issued on October 6, 2014. Construction commenced October 13, 2014. Construction was completed on December 5, 2014.
Design Start Date:
June 2014
Design End Date:
July 2014
Design % Complete:
100%
Construction Start Date:
October 2014
Construction End Date:
December 5, 2014
Construct. % Complete:
100%
Budget:
$124,076