Former EOC (new MCDRC) Refurbish As County Data Center

Refurbish former EOC (now called Martin County Disaster Recovery Center-MCDRC) as a Tier 2-3 data center to replace the County Admin Center data center as one of two primary data centers. PSC will remain as the other primary data center.

Dept:
ITS
District:
District 4
Status:
Active/Under Construction
Project Type:
Community Broadband Network Fiber
Project Number:
9096
Project Contact:
Denise Hunt,ITS Harold Markey,GSD
Current Status:
Inside construction nearlycompleted. FPL installied new power feed . Generator has been delivered and is in place, and testing completed. APC cabinets have been moved into the new data center and APC is working on the electrical and cooling systems. Network equipment has been procured and is ready for installation in the APC cabinets, once APC is done. Fiber between Transmitter Room to new Data Center has been installed and is ready for network switches.
Design Start Date:
03/01/2008
Design % Complete:
100%
Design End Date:
02/28/2017
Construction Start Date:
12/5/2016
Construct. % Complete:
95%
Construction End Date:
04/30/2017
Budget:
TBD
Project Coordination:
ITS,GSD,BLD,SO
Economic Development Project:
N/A
Location:
Martin County Disaster Recovery Center-MCDRC (former EOC) 6000 SE Tower Road, Stuart FL 34997