Halpatiokee Park Renovation Project Fiber to All Park Buildings

Extend CBN Fiber Network to Halpatiokee Park and connect all concession buildings, maintenance and other buildings to the fiber network.

Dept:
ITS
District:
District 4
Status:
Completed
Project Type:
Community Broadband Network Fiber
Project Contact:
Bob Burden,ITS
Current Status:
CBN fiber installation to Halpatiokee Park Maintenance (main) Building completed and site up and running on CBN network. Will next install network to concession stands and residence over the next week or so.
Design Start Date:
06/24/2016
Design % Complete:
100%
Design End Date:
11/18/2016
Construction Start Date:
12/6/2016
Construct. % Complete:
100%
Construction End Date:
02/01/2017
Budget:
$79,985.00 PCS Quote Including Tennis Courts. $10,000 est for network and wifi equipment.
Project Coordination:
ITS,PRD,GSD,PWD,SO
Economic Development Project:
No
Location:
Halpatiokee Park, 8303 SW Lost River Road, South Stuart